NAVFAC Washington 8(a) Small Business MACC – $750M

Doyon Management Services will be working with NAVFAC Washington on this eight-year Design-Build, Design-Bid-Build Multiple Award Construction Contract (MACC). Construction projects will include new construction, demolition, repair, alterations, and renovation of buildings, systems and infrastructure. Types of facilities may include administrative, industrial, maintenance, warehouses, communications, personnel support recreation, lodging, medical, training, ranges and roads in the NAVFAC Washington AOR.

USACE Locker Room and Restroom Renovation, Fort Belvoir, VA – $3.9M

Doyon Technical Services will be working with USACE Baltimore District on this 548 calendar day project to renovate the men’s and women’s locker and restroom areas to comply with the current codes, DoD Unified Facility Criteria (UFC) and the Americans with Disabilities Act (ADA). This renovation requires demolition of portions of the floor slab (slab on grade), includes an associated breakroom and exercise room, and requires work to the mechanical, electrical, and plumbing, fire protection systems, and associated building systems related to the renovated spaces.

USACE Carlisle PX HVAC Upgrades, Carlisle, PA – $1.9M

Doyon Technical Services will be working with USACE Baltimore District on this 365 calendar day Design-Build project to remove and replace three AHUs for the PX at Carlisle that was originally constructed in 1974.

USACE Technology Lab Office Reno, Ft. Detrick, MD – $3.2M

Doyon Technical Services will be working with USACE Baltimore on this 360 calendar day Design-Build project to provide MEP upgrades and cosmetic renovations to work areas on the second floor of the Technology Laboratory at Fort Detrick, MD.

USAF Repair East Apron B5009, Hill AFB, UT – $4.1M

Doyon Management Services will be working with the U.S. Air Force on this 365 calendar day project to provide full depth slab replacement of on select PCC panels and minor repairs on other panels on the section of the East Apron (about 236,000 SF of apron pavement located between Building 233 and Taxiway A) at Hill AFB, UT.

USACE Entomology Lab Renovation, WPAFB, FL – $492K

Doyon Project Services will be working with USACE Mobile District on this 270 calendar day Design-Build project to renovate the Entomology Laboratory, Building 20073, at Wright-Patterson AFB, OH.

USSF Repair Titan 115kV Substation, CCSFS, FL – $954K

Doyon Management Services will be working with the U.S. Space Force on this 210 calendar day Design-Build project to replace forty-five 115KV vertical bus support insulators, six-115KV ganged switches, thirty-nine 115KV suspension insulators and twenty-five galvanized structural support braces at the Titan Substation on Cape Canaveral Space Force Station, FL.

USACE Armory Repairs, South Bend, IN – $1.7M

USFS Seed Extractory Building Site Improvements, Bend, OR – $1.5M

Doyon Management Services will be working with the U.S. Forest Service on this 180 calendar day project to provide electrical, mechanical, and site improvements at multiple buildings at the Bend Seed Extractory in Bend, OR. Work includes connection of restrooms from two buildings to City of Bend sewer system, replacement of halon fire suppression systems with new clean agent systems in two buildings, and new electrical controls and process integration for multiple buildings. Optional work includes new power backup generator for seed freezer building and rebuild of tree cooler humidification system.

NAVFAC Shaft Lathe Electrical Foundation, PSNS, WA – $4.6M

Doyon Project Services worked with NAVFAC Northwest on this 260 calendar day Design-Build project to repair the customer’s shaft lathe foundation including electrical and incidental related work.