FHWA Tanana River Recreation Area Improvements, Fairbanks, AK – $8.6M
Doyon Management Services will be working with the Federal Highway Administration, Western Federal Lands Highway Division on this 558-calendar-day project to improve access to the Tanana Lake Recreation Area (TLRA) and to federally-managed lands along the Tanana River. Work will end by Fall of 2024. The scope of work includes:
• The project will begin at the South Lathrop Street and Sanduri Avenue intersection where an existing at-grade road/rail crossing will be replaced.
• Reconstructing South Lathrop Street to the Tanana flood control levee with a 32-foot-wide, paved driving surface.
• Extending South Lathrop Street approx. 1,700-feet beyond the Tanana flood control levee with a new 32-foot-wide, paved driving surface.
• Extending Northlake Lane approx. 500-feet to a new 4-way intersection with the new South Lathrop Street extension.
• Parking lot resurfacing and expansion of the Swim Beach Parking Lot, paving of the Motorized Boat Launch and Non-Motorized Boat Launch, new restroom installation, and 1500’ of ADA compliant pathway.
• Vehicle plug-in installation at the Motorized Boat Launch and Non-Motorized Boat Launch.