USBR Provo Area Office Cubicle Remodel – $1.8M

Doyon Management Services will be working with the U.S. Bureau of Reclamation on this 180 calendar day project to construct and complete Bureau of Reclamation Provo Area Office Cubicle Remodel including demolition, carpet, steel framed office walls and insulation, steel framed office ceilings and insulation, cubicle panels and electrical raceways, soundproof office doors, acoustic windows, furnishings, lighting, vents connected to the existing ductwork, electrical for each section of cubicles and offices, new cables from the servers for each section of cubicles and offices, and to relocate fire sprinklers.

NAVFAC 22SN Renovation, NSF Indian Head, MD – $6.3M

Doyon Management Services will be working with NAVFAC Washington on this 539 calendar day project to renovate the interior of building 22SN. The project will comply with all applicable SHPO requirements and security requirements for top secret open secure storage. Exterior work to include replacement of 3 pairs of existing large exterior doors: new door to match existing in size and appearance. Interior systems work to include modification of existing electrical, plumbing, and mechanical, fire alarm, and fire protection systems throughout the entire building. Interior bottom floor architectural work to include new floor and ceiling finishes, creation of workspaces and two unisex restrooms, and providing a delineation between the classified and unclassified zones. Interior top floor architectural work to include creation of a conference room. Due to building code requirements for egress the addition of an elevator and exterior stair is required for the top floor conference room. Proposed additions will comply with applicable SHPO requirements. Any incidental related work required for completion of project.

NAVFAC HVAC ICPB, Phase 1, B6589 SWFPAC, NBKB, WA – $2.5M

Doyon Management Services will be working with NAVFAC Northwest on this 270 calendar day project to replace HVAC System at ICPB, Phase 1, B6589, SWFPAC including (4) chillers, (4) chilled water (CHW) pumps, (3) hot water (HW) pumps, air handler #2, and return fan #5.

NAVFAC NRL-216 Install High Plume Exhaust System, DC – $5.6M

Doyon Management Services will be working with NAVFAC Washington on this 490 calendar day project to remove the exhaust duct and exhaust fans, provision of 316 stainless steel exhaust duct and rooftop high plume induced flow laboratory exhaust fan systems, integration of DDC controls with existing building DDC system and DDC front end located in building 57, patching and repairing of roof, shaft wall, shaft floor, and walls, painting, cleanup, and incidental related work while limiting disturbance to occupied lab spaces.

USCG M&R Campus HVAC Upgrade, New London, CT – $558K

Doyon Management Services will be working with the U.S. Coast Guard on this 133 calendar day project to

(1) the replacement of two packaged roof top units at Hamilton Hall
(2) removal of two server room raised floor AC units, one ductless split AC unit and provide variable refrigerant flow AC system consist of two outdoor condensing units and five indoor ductless AC units at Hamilton Hall
(3) replacement of four ductless split AC system servicing telecom rooms at Chase-E
(4) provide one ductless split AC system in the Police Department Room at Munro Hall
(5) removal one raised floor AC unit and provide variable refrigerant flow AC system consist of one outdoor condensing unit, two ductless AC units and one ducted air handler at Smith Hall’s Secret Internet Protocol Network (SPERNET) room.

NAVFAC B107/108 Paving Repair, NSA-Mechanicsburg, PA – $1.2M

Doyon Management Services will be working with NAFAC Mid-Atlantic on this 240 calendar day project to to pave the northern end of the 100 “Block” of H Street/Track. This is the area between Buildings 107 and 108 and First Avenue and extending southwards and encompassing approximately 10,000 square feet. The approximate area is delineated on the sketch in Part 6 Attachments. Existing gravel driving and storage areas shall be repaired via full depth reconstruction consisting of removal of old railroad ballast, a prepared subgrade, new 12” aggregate base course, necessary drainage improvements, and 12” reinforced Portland cement concrete paved area designed for tractor trailer loads and heavy forklift traffic. New pavement markings and signage are to be provided, these will be limited to signage and markings at the entrance and exit. Where possible, namely in areas around First Avenue, some areas should be converted to vegetated rain gardens with a sump (approximately 600 square feet), filter media, underdrain, liner, and connection to the existing storm sewer. An This procurement has one (1) option bid item. The first option bid item is CLIN 0002 for the use of schedule 40 piping for all new piping in accordance with the drawings and specifications.
The Bid Option is to pave the southern approximately 8000 square feet. The bid option would be to extend the drainage system and Portland cement concrete paving all the way to the bridge between Buildings 107 & 108. Existing distance between the dock heights and road level will be maintained.

NAVFAC D/B Replace SIM Center Roof and HVAC Unit, Silver Springs, MD – $1.0M

Doyon Management Services will be working with NAVFAC Washington on this 402 calendar day project to provide labor, approved materials, tools, mobilization, transportation, supervision and equipment necessary for replacement of the roof and add a new HVAC unit.

USCG Repair Cedar Lane Potable Water Main USCG Academy, New London, CT – $55K

Doyon Management Services will be working with the U.S. Coast Guard on this 42 calendar day project to repair a leak in the 10” PVC water main serving the Academy’s Maintenance Shops, Boiler Plant, Sail Loft, and all facilities east of the railroad tracks. The scope includes hiring an independent utility locator service to find and mark the location of the water main at the repair site (CBYD does not perform locating/marking services for Academy-owned utilities), excavation as required to repair the water main, backfill to pavement base course elevation with excavatable flowable fill, and HMA pavement restoration to match existing conditions. For bidding purposes, assume the water main is located 5’ below grade, that required repair materials include 5’ of 10” AWWA C900 DR 25 PVC water pipe and 2 NSF/ANSI 61 couplings, that an additional 1 CY of flowable fill will be needed to fill any undermining observed, and that pavement restoration entails 3” of HMA over 8” of processed aggregate base. Couplings shall be installed and tested per manufacturer instructions. Contractor shall saw cut and remove pavement 12” beyond the limits of excavation.

BLM Replace Vault Toilet, Elderberry Flats CG, Medfield District, OR – $95K

Doyon Management Services will be working with the Bureau of Land Management on this 150 calendar day project to provide Vault Toilet Replacement at Elderberry Flats Campground, for the BLM Medford District Office, Oregon.

NAVFAC Replace Existing Roof Systems, B7415, 7419, 7425, and 7428, NBK-Bangor, WA – $1.9M

Doyon Management Services will be working with NAVFAC Northwest on this 210 calendar day project to Remove and replace entire existing roofs, roof insulation, fascia, soffits, gutters, downspouts roof hatches and associated trims/fasteners on B7415, 7419, 7425 and 7428. Work on B7415, B7419 and B7425 to include Logistic Escape Trunk (LET) roof hatches, integrated hand railings and their electrical motors and actuators. Install snow guard systems to B7125 and B7142.